Best practices quiz: complete list of questions
and answers
In
the questions and answers below, "transmission" refers to installations
on lines >100 kV and "distribution" refers to installation on
lines < 100 kV. NESC refers to the National Electrical Safety
Code which governs all electric utility installations in the U.S.
(and any other jurisdictions that adopt it).
#1. (U.S.)
Do you still meet NESC clearance requirements at your worst case
wind storms and ice storms? Would your fiber survive these storms?
(Back to top)
First,
the code requires that you meet clearance requirements. Second,
you can be sued if you don't meet code and there's a problem.
Third, recent extensive research on ice storm historical data
has indicated that in many areas, your fiber network may likely
experience at least one ice storm exceeding NESC loading during
the life of your fiber network (we've got a tech note on this).
Finally, heavily sagging fiber cables blocking roads get cut by
cleanup crews if they're in the way.
#2. Did
you find any damaged (step attenuation increases of 0.1 dB or more?)
fibers after your installation was complete? (Back
to top)
It is reasonable to install hundreds of miles of ADSS or OPGW
without one damaged fiber (let alone broken fibers). These cables
contain either Kevlar (ADSS) or steel (OPGW) and are very strong
-- theoretically, you could tow a trailer with this stuff and
never damage a fiber.
We're defining "damaged" here as a step increase in
attenuation of at least 0.1 dB.
While a step increase of just 0.1 dB is an insignificant amount
of loss, it's an indication that something is pinching or stressing
the fiber. That small step increase could easily become a break
with a change in temperature or cable loading, depending on the
cause of the step.
Furthermore, from our failure analysis consulting work, we've
seen that certain types of installation damage can leave no external
marks on the cable and yet still significantly damage long runs
of the plastic (ADSS) or metal (OPGW) buffer tubes that protect
the fibers inside the cable. Small changes in temperature and
cable loading can cause the appearance (or disappearance) of attenuation
steps all along these damaged stretches -- if you have an 'event'
on one fiber, it may be a matter of time before you see more point
defects on other fibers.
Some utilities and installation contractors have become used
to a few damaged fibers during their installations and just shrug
it off as "something that happens". That's absolutely
wrong! Competent crews installing fiber cable under attentive
supervision and following proper procedures routinely install
fiber for years with no damaged fibers.
Depending on the circumstances behind a fiber fault, we may recommend
an entire reel be replaced even if there's only a fault in one
location.
#3. If
you did, did you know how they were damaged? (Back
to top)
This question is perhaps more important than the previous question.
As noted, faults don't "just happen". And one fault
may just be the tip of the iceberg -- if a long stretch of cable
is damaged, many more may just be waiting to appear with a change
in the weather.
If an installation crew used improper installation techniques
on one reel of cable, we've found they were likely to have done
it in many other places. It's critical to figure out exactly the
reason for any failure so you can determine where similar damage
was done.
Installation crews aren't the only possible culprits -- for instance,
designers can specify the wrong cable or hardware and hardware
manufacturers can ship the wrong cable attachments.
#4. Are
you sure they were damaged and not just an OTDR misinterpretation?
(Back to top)
We're
big believers in the usefulness and accuracy of OTDRs (Optical
Time Domain Reflectometers) -- two of us used to work for an OTDR
manufacturer. We think any utility with fiber should own an OTDR
(or mini-OTDR). Nevertheless, we've observed that the accuracy
and power of modern OTDRs often exceeds the skill of the operator
using it! Before "blowing the whistle" on fiber damage,
the operator should make sure they've got their instrument set
up correctly (we've got a tech note on proper OTDR setup). In
particular, they need to ensure they have enough dynamic range
and have selected the correct pulse width such that they're misinterpreting
noise (static) in the display as a glitch in the fiber.
#5. Can
you reconcile the differences between OTDR distances and actual
locations (Back to top)
OTDRs
are very accurate in determining the distance to a fault on a
fiber -- typically within a few feet. More accurate, in fact,
than the machine that prints the foot markings on the cable jacket
(which may be off by as much as 1%) and more accurate than most
utilities' as-built records. Finally, the OTDR operator needs
to enter the correct index of refraction value. It's reasonable
to expect an OTDR operator to nail the fault location within a
few feet, but it doesn't happen without proper training ahead
of time and good record-keeping. Otherwise, even with a properly-working
OTDR, it's common for technicians to be off by 1% to 2% on fault
locations -- that's 300 to 600 feet on a 6 mile run!
#6. Later,
did any fibers start displaying damage for reasons other than obvious
external causes (tornadoes, etc.)? (Back to top)
See
the answer to the next question.
#7. If
so, do you know why? (Back to top)
Most installation damage shows at least one fault during final
acceptance testing, but for the reasons explained above, it could
hide until a change in temperature or cable loading flexes a damaged
buffer tube and breaks or pinches a fiber. It's important to aggressively
track down the cause even for a minor fault to ensure it's not
likely to happen elsewhere.
Cable manufacturing quality for the manufacturers on our approved
list is exceptionally high -- fiber faults that occur are usually
going to be due to a different cause, but it's still important
to check each reel before ruling out manufacturing errors as a
cause.
#8. Do
you test incoming cable on the reel? If so, have you ever spotted
a defective fiber? Why do you test incoming cable? Do you keep all
the results? (Back to top)
As mentioned, cable quality is very, very high among our approved
vendors. They ship tens of thousands of good ADSS reels without
shipping a defective reel. All of the cable is 100% tested with
OTDRs and documented at the factory before shipping. Incoming
acceptance testing protects the cable purchaser from damage by
the shipping company.
Some users don't test fiber cable on incoming inspection and
we think that's a calculated risk to save time and money. We recommend
taking this extra step and documenting the results; doing so protects
the utility if a contractor subsequently damages the cable ("we
didn't do that -- the trucker must have damaged it!")
If by some chance, you did receive a defective reel of cable
on incoming inspection in the last 5 years, we'd be interested
to hear about it and who the vendor was.
Finally, we should note that OTDRs are good at spotting point
fiber defects on incoming reels. They are less accurate at measuring
dB/km -- you may often find your measurement of dB/m varies from
the factory's by 0.02 dB or so. Keep this in mind if you're trying
to measure vendor performance against dB/km specifications.
#9. Do
you know where all the long distance carriersÕ fiber cables serving
your area cross your route and have you made provisions for potentially
connecting to them in the future? (Back to top)
See
the answer to the next question
#10. Have
you identified additional corridors carriers might use in the future
and made provision to run taps to them in the future?
(Back to top)
Tying
your network to long distance carriers' fiber may increase the
potential revenues you can realize from dark fiber leases if you
can then connect them to local businesses on your route and enable
them to cut out the expense of going through the local carrier
(usually Bell). It's important to identify where these carriers
are crossing your route (or might in the future) and leave slack
storage at those locations to facilitate splicing in taps to their
fiber.
#11. Do
you know where those carriers' POPs are and have you made provision
to run taps to them in the future. (Back to top)
Some
long distance carriers may prefer to tie to your fiber network
at their local POP instead of making a direct fiber connection
at a point where their fiber cable crosses your route. You'll
want to know where their POPs are and make provision to runs taps
to them.
#12. Have
you identified the major potential business and institutional customers
near your routes and made provisions to run fiber taps to them?
(Back to top)
This
is a common sense question that would seem to require no explanation,
yet many utilities still overlook major opportunities. The key
is to identify who's using lots of expensive bandwidth, not who
has the tallest smokestacks.
Ironically,
large investor-owned utilities, so good at developing business
in big cities, are ignoring millions of dollars in potential revenue
as they fight ever tougher battles in big cities saturated with
fiber and competitors. They're not even entering the Tier 3 and
Tier 4 markets in their service areas, where there's no competition
besides Bell! Meanwhile, in adjacent small towns, municipal utilities
are profitably connecting many of the local businesses.
#13. If
building a network after September 11, 2001, have you talked to
local homeland security and law enforcement personnel about possibly
using your dark fiber for security video feeds? How about your own
internal security department -- do they want fibers for video cameras
at substations and other key assets? (Back to top)
September 11, 2001 changed the way we all look at security. Utility
security personnel are looking to better secure key assets in
their system. Local authorities are discovering new vulnerabilities
and moving to secure them. Security staffing can only increase
so quickly, so the demand for video surveillance systems and smart
sensors is growing. Security officials are now installing cameras
in new areas.
Additionally, a private fiber network is much more secure from
intrusion than a wireless network or traffic moving over the public
telecommunications network. Attackers can cut a fiber cable, but
they're almost impossible to tap. Combine fiber with self-healing
ring networks and utilities can offer local authorities increased
data security.
Planning in these areas by security officials is evolving from
day-to-day; perceived fiber needs may change from month to month.
If your network designers aren't in regular touch with internal
and external security personnel since 9-11, they should be.
#14. Do
you have a dark fiber marketing plan? Is someone actually working
it? (Back to top)
Again,
another common sense question, but one that many utilities flunk.
Some don't have a plan, some do but don't work it and others have
a plan -- but don't work it very effectively.
Getting
this going is hard for many utilities -- the skills and the thought
processes just haven't been required before in the rest of the
utility's business. This is an area where experienced outsiders
can help.
#15. Do
you require the cable vendor supply test reports from qualified
independent test labs (such as Kinectrics -- formerly known as Ontario
Hydro Technology) demonstrating compliance to IEEE standards for
OPGW and ADSS? (Back to top)
Special IEEE standards apply to most of the fiber cables that
utilities use; these are tailored to the special demands of power
utilities, not phone or cable TV companies. Only a few independent
labs worldwide have the facilities to perform these tests. Knowledgeable
utilities require vendors provide test reports from such labs
demonstrating successful performance on all of these tests. This
is an absolute requirement of Fiber Planners before we approve
any vendor's cable. (See our page on materials
tests.)
(Such tests are expensive -- tens of thousands of dollars --
so they are usually done once for an entire family of related
cables that share a common design. They're not done for every
customer or every order.)
#16. Do
you use any premium dispersion fibers (such as LEAF®, MetroCor,
AllWave®, or TrueWave®) in your network? If so, why? If
not, why? (Back to top)
LEAF®, MetroCor, AllWave®, and TrueWave® are
"premium" single-mode fibers with special dispersion
or attenuation characteristics to facilitate wavelength division
multiplexing (WDM). Naturally, they're more expensive than traditional
single-mode fiber. They offer no advantage when used in traditional
optical networking applications but are valuable in WDM applications.
Some utility network routes use cables consisting mostly of premium
fibers, others contain no premium fibers. Selecting the right
fibers for your routes requires an understanding both of how these
fibers work and what your future wavelength management needs may
be. If you don't know what you're using or why, you'll want to
go back to the books to learn more about current optical network
design.
#17. Do
you use any multimode fiber in your outside plant? If so, where
and why? (Back to top)
Multimode
fiber is used in corporate intra-building and campus local area
networks (LANs). It's almost never used in utility fiber optic
outside plant networks except occasionally in a few short links
within a substation or office building. If you're running ADSS
or OPGW with multimode in it, you need to ask why.
#18. Do
you have an emergency restoration kit? Do you have an emergency
restoration plan? Have you practiced it in the last 6 months? Last
year? (Back to top)
Utility ADSS and OPGW networks are the most reliable fiber networks
out there. As has often been said, "there are a lot more
backhoes than tornados" -- buried telco cables get cut much
more often than aerial power utility fiber cable systems.
Still, accidents can happen. Your own electric system and customers
are counting on you to get service back up fast. Well-rehearsed
restoration crews with pre-prepared restoration kits routinely
restore fiber service in 4 hours or less -- can you?
If you don't have a kit, a plan and regular drills, you're in
trouble. Routine OTDR checks (next question) are no substitute
for drills, but they can supplement drills by reinforcing troubleshooting
skills.
#19. How
often do you check your lines with an OTDR once they're in service?
(Back to top)
Checking at least your unused fibers periodically for attenuation
changes can identify signs of future trouble before it gets out
of hand. Having said that, those sorts of "creeping"
problems are unusual in well-built systems.
Much more importantly, periodic OTDR checks keep your crews familiar
with their OTDR, test access locations, as-built network records
and any details of particular routes.
#20. What
wavelengths do you test your fiber at? (Back to
top)
You should have OTDR records of every fiber on every route and
tested in each direction. Tests should be made at 1310 nm. and
1550 nm. Copies of these records should be kept both at a central
location and at the test locations. If not, you're not ready.
What about 1625 nm. tests? It's still an open question whether
to test at this new wavelength. Some networks will eventually
carry traffic at or near this longer wavelength, which is much
touchier for splicing mistakes. Many never will. What are your
future wavelength management plans? If you may operate at 1625
nm. in the future, you should get these tests done now as part
of your installation and splicing acceptance tests.
Even if you don't expect to operate at 1625 nm., it may still
be worthwhile to test at 1625 nm., just to spot kinked fibers
at splice cases, but it will add cost to your splicing contract,
especially if your contractor doesn't have a 1625 nm. OTDR module.
Industry opinions are divided on doing this.
#21. Does
your design meet all appropriate NESC standards? Was your system
built as specified or were things fudged? (Back
to top)
If you can't answer yes to both questions, you're headed for
trouble (see our litigation
consulting page.)
Especially on distribution lines, it can be hard to squeeze in
a fiber cable on to existing poles and still meet complex NESC
requirements without replacing a pole. It's tempting for designers
to either knowingly violate the code or, more commonly, specify
an code-compliant installation on a pole that's impossible to
actually install in the field.
Likewise, it's tempting for installers to install cable the easiest
way, not necessarily the specified (and code-compliant) way.
The answer is careful planning for each pole, clear pole-by-pole
instructions and attentive and careful project supervision.
#22. Have
you set up a CLEC, hybrid fiber/coax CATV network or FTTH (fiber
to the home) business or are you planning to? If so, did you get
an outside feasibility study? If so, was it by a potential vendor?
(Back to top)
Moving from dark fiber leasing to setting up a CLEC (competitive
local exchange company) or a cable TV operation is potentially
lucrative and we have clients already doing this successfully.
And taking fiber to the home is the ultimate potential home run
in fiber deployment.
All of these activities, however, call for greater financial
risks and investments as well as major organizational changes
and expansions at your utility -- think and plan carefully before
undertaking them. Get an outside feasibility study as a second
opinion (and be aware of the pitfalls in picking the wrong consultant
-- see our page on
feasibility studies.)
#23. If
you are offering CATV services, did you hire someone out of that
industry? If you've set up a CLEC, have you hired someone with telco
experience? (Back to top)
Running a cable TV system or a competitive telephone company
is sufficiently different from the power business that you need
to bring in at least some good talent with strong backgrounds
in the business you're entering -- yet we see utilities fail to
do this. Conversely, we've seen utilities staff up a new division
completely with outsiders -- yet it's important that at least
some of the technical and managerial personnel have strong backgrounds
in electric distribution design or construction.
#24. Do
you always use sheaves at least the diameter required by the manufacturer?
Do you know that diameter off the top of your head? Does someone
check the crews - at every pole or tower - to make sure they're
complying? (Back to top)
Never use a sheave smaller than that recommended in the cable
manufacturer's procedures unless you have specific approval to
do so from the vendors. Big sheaves are a real hassle, so line
crews will sometimes try to take shortcuts and use smaller, lighter,
easier-to-rig sheaves than approved by the manufacturer. Don't
do this -- we'd rather be your designer than your failure analysis
consultant! Undersized sheaves damage cable internally in ways
that may not be obvious from the outside. They void your cable
warranty, too. (We've got a tech note on sheaves.)
We'll ask one more time -- even if you say your installers don't
use undersized sheaves -- are you sure of this?
#25. Do
you ever use a cluster of smaller sheaves in order to get the bend
radius required of a large sheave? (Back to top)
Installers may either rig their own cluster of undersized pulleys
individually or use a "banana block" (also known as
a "quadrant block" or "three-block"), a set
of multiple small pulleys fixed in an arc. Using such methods
ensures the manufacturer's minimum bend radius specification is
met without having to struggle with heavy, full-sized sheaves.
But it's still a bad choice -- these arrangements do maintain
the correct bend radius, but they crush the cable by distributing
the weight over a tiny area on each of several small sheaves.
#26. What
fiber counts did you use? How did you pick those numbers?
(Back to top)
Choosing fiber counts on different routes involves an understanding
of who'll be using your fiber; expected future internal SCADA,
video, voice and data needs; whether you might go offering additional
services such as fiber to the home, CLEC services or cable TV
in the future; and your future wavelength management needs. Fiber
counts are also tied into your decision as to whether to use premium
fibers (see the earlier question on this topic.)
In theory, it's possible to use time division multiplexing (TDM)
and wavelength division multiplexing (WDM) to shoehorn all your
traffic and your customers' traffic onto just several fibers --
the fiber by itself has that much bandwidth. In reality, the network
equipment to do that much multiplexing is expensive and it's usually
much cheaper and easier to add more fiber to the cable. We have
small-town customers using 288-fiber cables in some areas.
#27. Does
your designer have fiber experience? If not (for instance, they
may be a staking engineer or transmission engineer), who trained
them on designing utility fiber installations? Does your designer
have utility line design experience? If not, who trained them on
designing fiber installation for utilities? (Back
to top)
Fiber optic networks require overlapping knowledge of both electric
utility operations and fiber optics. Few people start out with
both. How long have your designers been doing both?
Particularly with the recent slump in the cable TV and telephone
businesses, many CATV and telco design firms have started going
after the utility fiber business they ignored for many years.
As a group, without getting extensive training in utility line
design, they tend to produce designs on the surface that look
inexpensive but rapidly go over budget as unforeseen make-ready
expenses pile up. For instance, cable TV companies and telcos
lash fiber cable to steel messenger wires in the communications
space -- they're not allowed in the supply region. They use slightly
less expensive fiber cable and hardware and much cheaper installation
labor and equipment than power utilities use when installing ADSS
in the supply zone.
So designers with telco and CATV backgrounds design the same
way they always have, but this time the poles already have cable
TV and telephone company cables on them. On many poles there's
no room anymore for another lashed cable, so to meet NESC requirements
the pole has to be replaced (including moving drops, transformers,
etc.), driving make-ready costs through the roof. Since they have
no background in working in the supply region, they avoid using
ADSS in that area, even though with a little more upfront installation
expense, the utility could cut pole replacements to under 2%.
It usually only takes about 2 pole replacements per mile to make
lashed aerial cable installations more expensive than ADSS installations.
Designers with powerline design backgrounds and no fiber experience
usually don't specify the correct ADSS cable characteristics and
create big sag and tension concerns for the future of the installation.
ADSS has unique properties that must be understood in order to
design a 40 year life span system.
#28. (Buried
cable runs) Do you have a marker wire or marker balls to enable
locating your cable in the future or do you rely on cable markers?
(Back to top)
Most utility fiber cable is installed aerially, but there are
still underground runs -- usually around substations and in downtown
areas. It's good to use warning signs ("Do not dig -- fiber
optic cable") but they're not enough, especially since they
get knocked down and sometimes moved. An all-dielectric cable
has to be detectable to cable locator crews, which means either
burying a tracer wire with it or using electronic marker balls.
#29. (ADSS)
Do you ever use the "moving reel method of installation"?
(Back to top)
The moving reel method of aerial installation is typically used
with messenger supported cables. First, a messenger must be installed
on the aerial route using J-hooks at each structure. Then in a
separate step, a truck with a spindle mounted on the rear of the
truck or on a trailer is driven past each structure. As the truck
drives the route, a "lashing machine" is pulled on the
aerial line. The lashing machine can consist of a tie-wrap system
or a wrapping system using mono-filament (fishing line) to wrap
around the cable and messenger. There are a couple of complicated
situations that might occur. First, the route may require the
truck to oppose traffic or drive on the field side of the structure
where a ditch would inhibit the path.
Secondly, the structures may be so crowded in the communication
region that the operator has difficulty maneuvering the lashing
machine past the structure. Thirdly, the sag requirements to match
cables above and below may be so different that the new cable
may clash with existing cables at installation.
The moving reel method is only acceptable when a messenger is
used. The reason is that the structures are load balanced by the
messenger since the ends of the route will terminate in downguys.
If no messenger is used and ADSS is installed. The truck drives
by a structure and attaches the cable but the truck can not balance
the load on the structure since there is no backtension on the
reel. This is not possible since the truck is moving and a reel
brake would not be able to keep uniform pressure. The real danger
is when a dead-end structure is tensioned and the first dead-end
is applied. The uneven load is typically enough to bend a wood
distribution pole and break power crossarms. Conductors drop and
everyone is unhappy.
For these reasons, the moving reel method is never acceptable
for ADSS installations.
#30. (ADSS)
Do you use installation crews with cable TV or telephone fiber experience?
Do you use crews with a power installation background? If they have
a power background, who's trained them on installing fiber?
(Back to top)
Fiber optic networks require overlapping knowledge of both electric
utility operations and fiber optics. Installation crews with a
firm understanding of both may not be available. So which do you
use -- cable TV or telecommunications installers with years of
fiber cable experience but none of it in the utility's "supply"
space or traditional electric line construction personnel?
The answer is simple, go with the power-qualified line construction
crews (either contractors or in-house crews) and train them on
the specifics of fiber. Power utility fiber construction at the
worker level is 95% good, safe utility line construction methods
and 5% special fiber handling considerations.
We can train a good line construction crew that's new to fiber
in one day, supervise them for a few days, then turn over supervision
to our client (who we also train) with confidence they'll complete
the installation with no major problems.
In contrast, cable TV or telephone contractor crews just don't
have the equipment or the skills to work in the supply region.
It's too big an undertaking to retrain and re-equip them for utility
line construction just for your fiber project.
For Fiber Planners projects, we have an approved list of good
contractors we've worked with. We are also open to working with
other good installers our utility client likes and has worked
with. (If you want to recommend a good power line construction
crew to Fiber Planners, let us know.)
Finally, it may sound like we're down on line crews after our
comments about sheaves, etc. We're not -- most linemen are conscientious.
They work in a hazardous field where sloppiness can get them killed
or fired. In our failure analysis consulting, we find installation
problems usually involve lack of proper fiber installation training,
inadequate supervision and poor designs (or inadequate instructions
from the designer). Personnel turnover within crews after initial
training and project briefings can also cause problems; new personnel
should get the same training and be watched carefully initially
to make sure they know what they're doing with fiber.
#31. (ADSS)
What's the maximum line angle you use for tangents? Suspensions?
(Back to top)
In
designing for a 40 year life with little or no maintenance, it
pays to be conservative in selecting attachment hardware.
The
maximum line angle Fiber Planners recommends for tangents is 12
degrees, vertical or horizontal -- considerably more conservative
than what the hardware suppliers specify. This limit is based
on seeing others experience' using tangents for larger angles
then having them chafe through hardware over time as cable moves
back and forth to balance changes in cable loading.
The
inside surface of a tangent has grit to increase the fiction so
the cable doesn't easily slip until it has several hundred pounds
of uneven tension to make it move. That friction and abrasion
could damage the cable jacket and over time, damage the cable.
(See the next question for an answer to avoid this condition)
Also,
installers sometimes drill the attaching bolt into wood poles
at something other than a 90 degree angle -- either by mistake
or to avoid some obstruction. As a result, unless it's floated
with a shackle (see the next question) the tangent may already
effectively have a 10 to 15 degree on it before even considering
the line angle on the pole.
Related
to line angle limits are span length limitations when using tangents.
Conservative designers usually avoid tangents on spans over 400
feet even if the vendor claims it can be used for longer spans.
Above 400 feet, we recommend using Armor Grip Suspensions (AGS)
and we limit their use to angles 25 degrees and under; for larger
angles we use dead-ends.
#32. (ADSS)
Do you "float" your tangents and suspensions with a shackle?
(Back to top)
If
you want a 40 year life with little or no maintenance, then Fiber
Planners strongly recommends the use of an anchor shackle with
each tangent and suspension to "float" the hardware.
The anchor shackle allows the hardware to shift temporarily an
inch or two to equalize uneven tensions at the pole, due to wind
or ice. Once the external force is gone, the anchor shackle can
shift back to balance the pole.
If
the "fixed" tangent design is used, the cable physically
moves from one side of the pole, through the hardware and into
the longer span to equalize the load. Once the temporary weather
condition is gone, someone must physically go to each piece of
hardware and manually shift the cable back through the hardware.
This is unrealistic when designing for a 40 year life with little
or no maintenance, as we do. In most cases, the extra sag will
stay in the longer span for years until it interferes with other
cables or something on the ground.
Letting
tangents and suspensions float also compensates for any bolt holes
not drilled perpendicular to the pole (see the previous question.)
#33. (ADSS)
WhatÕs the ratio of dead-ends to tangents in your system? Dead-ends
to suspensions? (Back to top)
The
ratio of dead-ends to tangents is not as critical as realizing
that it takes many more dead-end structures to design an ADSS
system than there are utility-labeled dead-end structures on your
system. Fiber dead-ends are needed at storage loops, highway crossings,
railroad crossings, windy valley crossings, vertical inclines
and many more system features, even if these are not considered
dead-end structures for the conductors. Experience and judgment
are needed since the hardware manufacturer's instructions don't
explain all the field conditions and their requirements.
If
a tangent or suspension is installed where a dead-end is required,
the cable will take the abuse of the friction or tension until
failure starts. The bolt holding it to the structure may shear
or the cable jacket may be rubbed enough to wear a hole in the
material leading to later Kevlar® failure and a loss of the
cable's tensile strength. Finally the cable will just fail and
fall to the ground.
#34. (Distribution
- U.S.) Do you always comply with the NESC requirements for clearances
and for maintaining a 40" safety zone? (Back to
top)
The
NESC is complex and has a number of exceptions to the 40"
safety zone for certain power utility equipment like streetlights.
But except for limited situations where 30" may be permissible,
40" is the required spacing between any ADSS in the supply
region and the highest communications cable. As long as that limit
is met, the NESC gives considerable flexibility as to where to
place the ADSS in the supply region -- above the neutral, below
the neutral, on an extension arm, attached to a crossarm, etc.
Also, a designer can sometimes shift around other power utility
items on the pole such as streetlights to get enough room for
a good attachment location.
Even
then, it can be quite challenging to determine an NESC-compliant
attachment point on a "fully loaded" pole (crowded safety
zone, transformer, downguys, streetlight, etc.) that installers
can actually install without damaging the cable. Also, there's
the requirement for 4" bolt spacing. The designer still has
to understand power distribution design and construction well
enough to come up with designs that are not too dangerous for
linemen to install and don't hamper future line maintenance, such
as transformer change-outs. Inexperienced ADSS designers may end
up with more pole replacements until they've designed a number
of routes.
If
the power utility uses fiber cable lashed to a steel messenger,
it must stay in the communications region. If there's not that
40" space between this new lashed cable and the supply region,
the utility can't attach to the pole without replacing it first.
(Our understanding of the NESC is that the 30" exception
is only available for supply region lines encroaching on the safety
zone from above, not for communications cables encroaching on
it from below.) Extension arms are not allowed. Pole replacements
are more common in this situation than even with a totally inexperienced
ADSS designer.
Our
clients' experience is that pole replacement including moving
over everything on the existing pole ranges from $500 (new simple
pole) to $5000 (fully-loaded pole: telco and cable TV cables,
transformer, multiple power circuits, etc.) Unfortunately, it's
the more loaded poles that usually require replacement.
#35. (Distribution)
What per cent of poles do you typically have to replace on ADSS
projects in order to maintain NESC clearances?
(Back to top)
Our
own experience is a pole replacement rate under 1% to 2% on most
projects.
#36. (Distribution)
Do you run ADSS on any routes where you have a history of insulator
contamination problems? If so, did you consider dry-band arcing
in your design? (Back to top)
In
North America, dry band arcing (DBA) is not normally a consideration
on lines under 100 kV. In areas of heavy pollution, failures have
occurred on lower voltage lines in this country in a few rare
cases. If your existing distribution plant has insulator contamination
problems in certain areas, you should consider analyzing the DBA
potential more closely as you would for transmission lines. If
warranted, you may want to install a tracking-resistant cable.
Outside
North America, reports of failure in lower voltage environments
are more common. We have a tech note that goes into electric field
effects in detail.
#37. (Transmission)
Do you sag your OPGW and ADSS with a dynamometer, sight lines or
a stop watch? If an outside contractor installs your cable, does
someone from your utility check the sags? (Back
to top)
ADSS
can't be sagged with a stopwatch. Depending on the particular
designs, stopwatch sagging may be possible with most OPGW.
ADSS
on transmission lines should always be sight-sagged using sight
lines provided by the designer.
Dynamometers
are useful installation tools but are subject to certain limitations:
their accuracy in estimating tension on the actual section being
sagged deteriorates if there are many spans between the dynamometer
and the span being sagged. More importantly, ask your installer
when he last sent his dynamometer to a certified calibration shop
("a certified what?"). We recently worked on a failure
analysis study where 40 miles of ADSS was systematically installed
using a dynamometer (but no sight sagging) at tensions 20% to
50% less than specified.
#38. (Transmission)
Do you use OPGW or ADSS on your transmission lines? How did you
pick which to use? (Back to top)
Both
OPGW and ADSS have their place on utility transmission systems.
Nevertheless, many utilities are either "OPGW bigots"
or "ADSS zealots" because they're comfortable with one
product and have either heard bad things or had a screwed up installation
with the other product. Either way it's a mistake. For more information
on the pros and cons of each, technology advisory subscribers
can refer to our tech note on the subject.
#39. (Transmission
- OPGW only) Have you had any OPGW failures due to lightning? If
so, how many? How did you pick the fault-current rating for your
cable? (Back to top)
OPGW,
like traditional groundwire, occasionally suffers lighting damage
to one or more wires in the outer layer; like traditional groundwire,
these spots are repaired using armor rods. OPGW and regular groundwire
are, after all, intentionally designed to be struck by lightning
and to safely conduct the strikes to ground.
Recently,
there's been an undercurrent of negative rumors about outright
OPGW failures (not just damage) due to lighting. Yet actual reports
are hard to pin down (if it's happened to you, we'd like to know
more -- please contact us). We're
only aware of 3 utilities where this occurred in the last decade
but one of those utilities experienced multiple failures. Interestingly,
we haven't heard of any in Florida, the state with both the highest
incidence of lightning and the most installed OPGW. Were these
failures a result of poor system design or bad luck?
In
any event, even with these failures, OPGW's reliability track
record remains outstanding.
#40. (Transmission
- ADSS only) Do you use corona coils? If so, do your inspectors
check to ensure that they've all been put on? Do you use vibration
dampers? Again do you check that all get installed?
(Back to top)
ADSS
installed in high voltage environments can be damaged by corona
effects occurring at the ends of the attach hardware. Corona coils
prevent this.
Corona
coils can be hard to install if bucket trucks aren't in use and
the dead-ends are long, since the installer has to lean out far
in the air to shove them over the end of the hardware. Vibration
dampers also require similar skill to put on if the dead-ends
are long. As a result, occasionally a damper or corona coil may
be accidentally left off. System acceptance inspection should
include a careful check of every span that neither has been left
off.
Towers
at the bottom of hills should be inspected after heavy ice storms
to ensure melting ice has not slid down and knocked dampers off
the line.
#41. (Transmission)
Is your ADSS cable at or above the elevation of any conductors at
any point on any span? If so did you do blow-out checks at your
local worst case windstorm and worst case ice storm to ensure the
ADSS would not collide with the conductors (and possibly wrap around
them)? Did you do these checks at intermediate wind speeds and ice
loads? Did you do icestorm blowout checks with both ice on and ice-off
conditions for your conductors? (Note, these questions don't apply
to OPGW in the normal high position; they do apply if you underbuilt
with OPGW or a similar metallic cable) (Back to
top)
See
our page on transmission
design page for more information -- all of these checks have
to be made for each span to ensure cable to conductor collisions
and entanglements do not occur as they have at some utilities.
#42. (Transmission)
If you built with OPGW above your conductors, did you do OPGW to
conductor clash studies for both ice on and ice off the conductors?
(Back to top)
See
our transmission
design page for more information -- both conductor icing scenarios
have to be checked since resistive heating may or may not keep
the conductors warm enough to be ice free.
#43. (Transmission
- ADSS only) Did you perform an electric field analysis on all ADSS
installations over 100 kV to ensure you won't have dry band arcing
problems? If so, did you use isovolt plots or jacket current models
or both? Did you correct the isovolt plots for tower line angle
and insulator swing angles? Did you use the correct phasing in your
model? If it was on a double circuit transmission line, did you
run studies with one side de-energized? If another transmission
runs parallel to this one in the same corridor, did you check to
see if it had an effect on your transmission line?
(Back to top)
See
our transmission
design page. Isovolt plots at a minimum are required for all
these scenarios and with the proper insulator and tower angle
correction factors. Jacket current analysis is a new analytical
technique we also use.
Questions:
>>page 1 >page
2 >page 3 >page
4 >page 5
Answers:
>>page 1
>page 2 >page
3 >page 4 >page
5 |