Best practices quiz: answers for question page 5
Answer
page 5 (of 5)
In
the questions and answers below, "transmission" refers to installations
on lines >100 kV and "distribution" refers to installation on
lines < 100 kV. NESC refers to the National Electrical Safety
Code which governs all electric utility installations in the U.S.
(and any other jurisdictions that adopt it).
You
can work through the questions on all 5 pages, then look at the
answers; take the questions one page at a time followed by their
corresponding answer page; or hop back and forth by following the
shortcuts at the end of every question or answer. Finally, if, like
many people, you get sick of all the clicking, you can just go to
one long page with all
the questions and answers.
#41. (Transmission)
Is your ADSS cable at or above the elevation of any conductors at
any point on any span? If so did you do blow-out checks at your
local worst case windstorm and worst case ice storm to ensure the
ADSS would not collide with the conductors (and possibly wrap around
them)? Did you do these checks at intermediate wind speeds and ice
loads? Did you do icestorm blowout checks with both ice on and ice-off
conditions for your conductors? (Note, these questions don't apply
to OPGW in the normal high position; they do apply if you underbuilt
with OPGW or a similar metallic cable) (Shortcut
back to question page 5)
See
our page on transmission
design page for more information -- all of these checks have
to be made for each span to ensure cable to conductor collisions
and entanglements do not occur as they have at some utilities.
#42. (Transmission)
If you built with OPGW above your conductors, did you do OPGW to
conductor clash studies for both ice on and ice off the conductors?
(Shortcut
back to question page 5)
See
our transmission
design page for more information -- both conductor icing scenarios
have to be checked since resistive heating may or may not keep
the conductors warm enough to be ice free.
#43. (Transmission
- ADSS only) Did you perform an electric field analysis on all ADSS
installations over 100 kV to ensure you won't have dry band arcing
problems? If so, did you use isovolt plots or jacket current models
or both? Did you correct the isovolt plots for tower line angle
and insulator swing angles? Did you use the correct phasing in your
model? If it was on a double circuit transmission line, did you
run studies with one side de-energized? If another transmission
runs parallel to this one in the same corridor, did you check to
see if it had an effect on your transmission line? (Shortcut
back to question page 5)
See
our transmission
design page. Isovolt plots at a minimum are required for all
these scenarios and with the proper insulator and tower angle
correction factors. Jacket current analysis is a new analytical
technique we also use.
You're finished!
Questions:
>>page 1 >page
2 >page 3 >page
4 >page 5
Answers:
>>page 1
>page 2 >page
3 >page 4 >page
5
Link
to long page with all questions
and their answers |