Best practices quiz: answers for question page 3
Answer
page 3 (of 5)
In
the questions and answers below, "transmission" refers to installations
on lines >100 kV and "distribution" refers to installation on
lines < 100 kV. NESC refers to the National Electrical Safety
Code which governs all electric utility installations in the U.S.
(and any other jurisdictions that adopt it).
You
can work through the questions on all 5 pages, then look at the
answers; take the questions one page at a time followed by their
corresponding answer page; or hop back and forth by following the
shortcuts at the end of every question or answer. Finally, if, like
many people, you get sick of all the clicking, you can just go to
one long page with all
the questions and answers.
#21. Does
your design meet all appropriate NESC standards? Was your system
built as specified or were things fudged? (Shortcut
back to question page 3)
If you can't answer yes to both questions, you're headed for
trouble (see our litigation
consulting page.)
Especially on distribution lines, it can be hard to squeeze in
a fiber cable on to existing poles and still meet complex NESC
requirements without replacing a pole. It's tempting for designers
to either knowingly violate the code or, more commonly, specify
an code-compliant installation on a pole that's impossible to
actually install in the field.
Likewise, it's tempting for installers to install cable the easiest
way, not necessarily the specified (and code-compliant) way.
The answer is careful planning for each pole, clear pole-by-pole
instructions and attentive and careful project supervision.
#22. Have
you set up a CLEC, hybrid fiber/coax CATV network or FTTH (fiber
to the home) business or are you planning to? If so, did you get
an outside feasibility study? If so, was it by a potential vendor?
(Shortcut
back to question page 3)
Moving from dark fiber leasing to setting up a CLEC (competitive
local exchange company) or a cable TV operation is potentially
lucrative and we have clients already doing this successfully.
And taking fiber to the home is the ultimate potential home run
in fiber deployment.
All of these activities, however, call for greater financial
risks and investments as well as major organizational changes
and expansions at your utility -- think and plan carefully before
undertaking them. Get an outside feasibility study as a second
opinion (and be aware of the pitfalls in picking the wrong consultant
-- see our page on
feasibility studies.)
#23. If
you are offering CATV services, did you hire someone out of that
industry? If you've set up a CLEC, have you hired someone with telco
experience? (Shortcut
back to question page 3)
Running a cable TV system or a competitive telephone company
is sufficiently different from the power business that you need
to bring in at least some good talent with strong backgrounds
in the business you're entering -- yet we see utilities fail to
do this. Conversely, we've seen utilities staff up a new division
completely with outsiders -- yet it's important that at least
some of the technical and managerial personnel have strong backgrounds
in electric distribution design or construction.
#24. Do
you always use sheaves at least the diameter required by the manufacturer?
Do you know that diameter off the top of your head? Does someone
check the crews - at every pole or tower - to make sure they're
complying? (Shortcut
back to question page 3)
Never use a sheave smaller than that recommended in the cable
manufacturer's procedures unless you have specific approval to
do so from the vendors. Big sheaves are a real hassle, so line
crews will sometimes try to take shortcuts and use smaller, lighter,
easier-to-rig sheaves than approved by the manufacturer. Don't
do this -- we'd rather be your designer than your failure analysis
consultant! Undersized sheaves damage cable internally in ways
that may not be obvious from the outside. They void your cable
warranty, too. (We've got a tech note on sheaves.)
We'll ask one more time -- even if you say your installers don't
use undersized sheaves -- are you sure of this?
#25. Do
you ever use a cluster of smaller sheaves in order to get the bend
radius required of a large sheave? (Shortcut
back to question page 3)
Installers may either rig their own cluster of undersized pulleys
individually or use a "banana block" (also known as
a "quadrant block" or "three-block"), a set
of multiple small pulleys fixed in an arc. Using such methods
ensures the manufacturer's minimum bend radius specification is
met without having to struggle with heavy, full-sized sheaves.
But it's still a bad choice -- these arrangements do maintain
the correct bend radius, but they crush the cable by distributing
the weight over a tiny area on each of several small sheaves.
#26. What
fiber counts did you use? How did you pick those numbers? (Shortcut
back to question page 3)
Choosing fiber counts on different routes involves an understanding
of who'll be using your fiber; expected future internal SCADA,
video, voice and data needs; whether you might go offering additional
services such as fiber to the home, CLEC services or cable TV
in the future; and your future wavelength management needs. Fiber
counts are also tied into your decision as to whether to use premium
fibers (see the earlier question on this topic.)
In theory, it's possible to use time division multiplexing (TDM)
and wavelength division multiplexing (WDM) to shoehorn all your
traffic and your customers' traffic onto just several fibers --
the fiber by itself has that much bandwidth. In reality, the network
equipment to do that much multiplexing is expensive and it's usually
much cheaper and easier to add more fiber to the cable. We have
small-town customers using 288-fiber cables in some areas.
#27. Does
your designer have fiber experience? If not (for instance, they
may be a staking engineer or transmission engineer), who trained
them on designing utility fiber installations? Does your designer
have utility line design experience? If not, who trained them on
designing fiber installation for utilities? (Shortcut
back to question page 3)
Fiber optic networks require overlapping knowledge of both electric
utility operations and fiber optics. Few people start out with
both. How long have your designers been doing both?
Particularly with the recent slump in the cable TV and telephone
businesses, many CATV and telco design firms have started going
after the utility fiber business they ignored for many years.
As a group, without getting extensive training in utility line
design, they tend to produce designs on the surface that look
inexpensive but rapidly go over budget as unforeseen make-ready
expenses pile up. For instance, cable TV companies and telcos
lash fiber cable to steel messenger wires in the communications
space -- they're not allowed in the supply region. They use slightly
less expensive fiber cable and hardware and much cheaper installation
labor and equipment than power utilities use when installing ADSS
in the supply zone.
So designers with telco and CATV backgrounds design the same
way they always have, but this time the poles already have cable
TV and telephone company cables on them. On many poles there's
no room anymore for another lashed cable, so to meet NESC requirements
the pole has to be replaced (including moving drops, transformers,
etc.), driving make-ready costs through the roof. Since they have
no background in working in the supply region, they avoid using
ADSS in that area, even though with a little more upfront installation
expense, the utility could cut pole replacements to under 2%.
It usually only takes about 2 pole replacements per mile to make
lashed aerial cable installations more expensive than ADSS installations.
Designers with powerline design backgrounds and no fiber experience
usually don't specify the correct ADSS cable characteristics and
create big sag and tension concerns for the future of the installation.
ADSS has unique properties that must be understood in order to
design a 40 year life span system.
#28. (Buried
cable runs) Do you have a marker wire or marker balls to enable
locating your cable in the future or do you rely on cable markers?
(Shortcut
back to question page 3)
Most utility fiber cable is installed aerially, but there are
still underground runs -- usually around substations and in downtown
areas. It's good to use warning signs ("Do not dig -- fiber
optic cable") but they're not enough, especially since they
get knocked down and sometimes moved. An all-dielectric cable
has to be detectable to cable locator crews, which means either
burying a tracer wire with it or using electronic marker balls.
#29. (ADSS)
Do you ever use the "moving reel method of installation"? (Shortcut
back to question page 3)
The moving reel method of aerial installation is typically used
with messenger supported cables. First, a messenger must be installed
on the aerial route using J-hooks at each structure. Then in a
separate step, a truck with a spindle mounted on the rear of the
truck or on a trailer is driven past each structure. As the truck
drives the route, a "lashing machine" is pulled on the
aerial line. The lashing machine can consist of a tie-wrap system
or a wrapping system using mono-filament (fishing line) to wrap
around the cable and messenger. There are a couple of complicated
situations that might occur. First, the route may require the
truck to oppose traffic or drive on the field side of the structure
where a ditch would inhibit the path.
Secondly, the structures may be so crowded in the communication
region that the operator has difficulty maneuvering the lashing
machine past the structure. Thirdly, the sag requirements to match
cables above and below may be so different that the new cable
may clash with existing cables at installation.
The moving reel method is only acceptable when a messenger is
used. The reason is that the structures are load balanced by the
messenger since the ends of the route will terminate in downguys.
If no messenger is used and ADSS is installed. The truck drives
by a structure and attaches the cable but the truck can not balance
the load on the structure since there is no backtension on the
reel. This is not possible since the truck is moving and a reel
brake would not be able to keep uniform pressure. The real danger
is when a dead-end structure is tensioned and the first dead-end
is applied. The uneven load is typically enough to bend a wood
distribution pole and break power crossarms. Conductors drop and
everyone is unhappy.
For these reasons, the moving reel method is never acceptable
for ADSS installations.
#30. (ADSS)
Do you use installation crews with cable TV or telephone fiber experience?
Do you use crews with a power installation background? If they have
a power background, who's trained them on installing fiber? (Shortcut
back to question page 3)
Fiber optic networks require overlapping knowledge of both electric
utility operations and fiber optics. Installation crews with a
firm understanding of both may not be available. So which do you
use -- cable TV or telecommunications installers with years of
fiber cable experience but none of it in the utility's "supply"
space or traditional electric line construction personnel?
The answer is simple, go with the power-qualified line construction
crews (either contractors or in-house crews) and train them on
the specifics of fiber. Power utility fiber construction at the
worker level is 95% good, safe utility line construction methods
and 5% special fiber handling considerations.
We can train a good line construction crew that's new to fiber
in one day, supervise them for a few days, then turn over supervision
to our client (who we also train) with confidence they'll complete
the installation with no major problems.
In contrast, cable TV or telephone contractor crews just don't
have the equipment or the skills to work in the supply region.
It's too big an undertaking to retrain and re-equip them for utility
line construction just for your fiber project.
For Fiber Planners projects, we have an approved list of good
contractors we've worked with. We are also open to working with
other good installers our utility client likes and has worked
with. (If you want to recommend a good power line construction
crew to Fiber Planners, let us know.)
Finally, it may sound like we're down on line crews after our
comments about sheaves, etc. We're not -- most linemen are conscientious.
They work in a hazardous field where sloppiness can get them killed
or fired. In our failure analysis consulting, we find installation
problems usually involve lack of proper fiber installation training,
inadequate supervision and poor designs (or inadequate instructions
from the designer). Personnel turnover within crews after initial
training and project briefings can also cause problems; new personnel
should get the same training and be watched carefully initially
to make sure they know what they're doing with fiber.
Go on to question
page 4
Questions:
>>page 1 >page
2 >page 3 >page
4 >page 5
Answers:
>>page 1
>page 2 >page
3 >page 4 >page
5
Link
to long page with all questions
and their answers |